South Howard Avenue is scheduled for nearly four years of construction, and the work is phased block by block. Tampa's plan for the South Howard Flood Relief and Streetscape Project begins at Bayshore Boulevard and works north in short sections. Each section reopens before the crews move on. So the corridor Hyde Park uses for dinner, coffee and late nights will be dug up one block at a time, and the order is already published. Utility relocation comes first, but the city's schedule puts the main culvert digging on South Howard after Gasparilla. That makes the 2026 holidays and the January parade the last stretch before that digging begins. Two lawsuits now decide how firm that schedule is.
A Schedule Built Around the Parade
Tampa City Council approved the $100.44 million project on September 17 by a 4-3 vote. The total combines $7.73 million in design work already authorized with a $92.71 million construction price from Kimmins Contracting Corp., as Tampa Bay Business Weekly reported. The project builds a large stormwater system beneath South Howard and West Swann. Its goal is to relieve flooding in Parkland Estates and Palma Ceia Pines, according to the project's own site.
The construction timeline presented to council that day reads like a calendar of the next four years:
- October 2026: notice to proceed, as scheduled
- November 2026: utility relocation scheduled to begin
- March 2027: triple box culvert extension at Bayshore Boulevard
- May 2027: box culvert construction starts on South Howard
- May 2028: CSX railroad crossing
- February 2029: West Morrison Avenue intersection
- October 2029: West Swann Avenue intersection
- May 2030: Parkland Estates
- September 2030: substantial completion
The 2027 Gasparilla Pirate Fest is set for Saturday, January 30, 2027, with the parade running along Bayshore Boulevard. FOX 13 reported that construction remains on track to start "after Gasparilla, in spring 2027." The utility relocation slotted for November is groundwork. Crews move existing lines before the culvert can go in. The digging that changes how the street works starts at the Bayshore end once the parade crowds clear.
Why "Four Years" Overstates the Wait for Any One Block
The headline figure covers the whole route. The corridor itself is broken into about 7,000 feet of stormwater conveyance, including a box culvert roughly 10 feet wide and 10 feet tall. It runs north from near Bayshore beneath South Howard to Swann, then west toward Audubon Avenue before turning north. Tampa divided that route into 24 zones of roughly 400 to 600 feet each. Completed sections are restored and reopened as the crews move north.
The city's FAQ describes the same approach in plainer terms. Kimmins must open one segment to traffic before starting the next, though some activities may overlap. At the scale of a single property, the design-build team estimates an individual driveway could be inaccessible for 5 to 7 weeks. During that time it plans temporary driveways and walkways, plus an off-site parking area staffed around the clock with a golf cart shuttle.
Blind Tiger Coffee Roasters at 934 South Howard shows what this looks like for one business. The Tampa Bay Times reported that construction is slated to start in front of that shop between the second and third quarters of 2027 and to be completed in the first half of 2028. That is about a year at one address, inside a project that runs to September 2030.
The work hours matter for a dining street. Construction is scheduled for 7 a.m. to 7 p.m., Monday through Friday. Weekend and nighttime work happens on a limited basis when deemed necessary. Most of SoHo's dinner service and weekend traffic falls outside those hours. During the day, though, the block in front of a business can look very different.
Bayshore drivers will notice the Bayshore end first. The FAQ says the two southbound lanes of Bayshore Boulevard will close for about 8 to 10 weeks. During that time one northbound lane will carry southbound traffic, leaving one lane each way.
Where the Named Places Sit
These are the addresses most likely to come up as the work moves north, along with what each holds today.
| Address | Business | What's there |
|---|---|---|
| 717 S. Howard Ave. | The Landon | Michael Stewart's New American restaurant in the former 717 South space |
| 901 S. Howard Ave. | Meeting House | Took over the Daily Eats space and began serving August 20, 2026 |
| 934 S. Howard Ave. | Blind Tiger Coffee Roasters | Opened on South Howard in 2018 as the roaster's fourth shop |
| 1207 S. Howard Ave. | Epicurean Hotel | Home to Élevage SoHo Kitchen & Bar and EDGE Rooftop Cocktail Lounge |
| 1208 S. Howard Ave. | Bern's Steak House | Directly across from the Epicurean |
Two of these are new to the street this year. That's So Tampa reported The Landon open by late March 2026. The Tampa Bay Times reported that Meeting House began serving August 20, with a ribbon-cutting on August 25. Both opened knowing the construction schedule was coming.
What the City Has Promised the Storefronts
Tampa and Kimmins published a Business Assistance Plan for the corridor. Its commitments are specific:
- Work limited to sections of about 400 to 600 feet at a time, with pavement, sidewalks and streetscape restored as each one finishes
- Safe walking routes and clear signage so customers can reach businesses inside active zones
- A four-person Kimmins team that works directly with merchants on construction problems, including coordinating deliveries
- Newer backup alarms on heavy equipment to cut unnecessary noise
- Independent vibration monitoring, plus photo documentation of buildings along the route before work begins
- A city marketing campaign called SohOPEN, using social media, billboards and other advertising to remind people that South Howard businesses are open during construction
The finished street is also part of the plan. The project includes new 10-foot-wide sidewalks on Howard, traffic calming, improved crossings, better street lighting, upgraded landscaping and permeable pavers.
Business owners do not all see these measures the same way. Roberto Torres of Blind Tiger told the Tampa Bay Times that "there's going to be winners and losers." He said that when he asked the city about relief, its answer was the marketing campaign. In the same article he said it "remains to be seen, how effective it is going to be when there's a 10-foot by 10-foot hole in front of our store in the middle of December."
Two Lawsuits Sit on Top of the Schedule
The timeline above is the city's. Since early October it has been under legal challenge. FOX 13 reported that Bern's Steak House, companies tied to Ciccio Restaurant Group and the Epicurean Hotel filed two class-action lawsuits. The defendants are the City of Tampa, Mayor Jane Castor, Kimmins and the engineering firm AtkinsRéalis USA.
According to that report, the first suit alleges the city redirected $13.4 million in stormwater assessment money without a required public hearing, and that the construction contract was awarded improperly. The second argues that Tampa holds an easement for the street surface but lacks the property rights to dig beneath it. The plaintiffs are asking a judge to block construction until the disputes are resolved. The city told FOX 13 it cannot comment on pending litigation.
The Tampa Bay Times named the businesses representing the class in the second suit: Sweet Soul, Water + Flour, Green Lemon, Meeting House and the Epicurean Hotel. Four of those are Ciccio Restaurant Group concepts. Élevage and EDGE are managed by Bern's Steak House Group. David Laxer, owner and president of Bern's Steak House Group, told the paper that closing portions of SoHo is estimated to bring "anywhere from a 25-45% drop in business," a figure he presented as an estimate. WTSP reported that no hearing date had been set for either requested injunction. FOX 13 noted that the spring 2027 start could change if a judge orders the city to pause the project.
So for now, the start date depends on how a judge rules on the injunction requests, and the order of the work depends on the engineering plan.
The Season Before the First Zone
The next few weeks on the Hyde Park side of South Howard follow the usual holiday schedule. Hyde Park Village's Holiday Happening runs Thursday, November 19, from 5:30 to 8 p.m. It includes live music, a Tampa City Ballet performance, Santa and a tree lighting at 7:45 p.m. The Fresh Market at Hyde Park Village returns Sunday, December 6, from 10 a.m. to 3 p.m., with more than 90 vendors. Gasparilla follows on January 30. According to the published schedule, the Bayshore culvert work comes after that in March, and South Howard follows in May.
Closures and detours will be posted on the project's Alerts page as work begins. The project team also says property owners, residents and tenants will be told in advance before access is affected. The project hotline is 813-467-7887, and the city lists [email protected] and 813-274-3326 for project questions.
If you own property near South Howard, or in Palma Ceia along the project's route, construction timing can affect when you list, how buyers reach your property and how your home is shown. KVA Group follows the SoHo schedule block by block, and we can plan a sale or purchase around it. Request a Confidential Consultation.